    A massive washout destroyed a portion of Upper icicle Road

outside Leavenworth in 2008. At that time there were no funds to fix the road into the popular enchantments

wilderness area. Finally, work began last summer and will officially wrap up in time for a re-opening of the road

this Saturday.
    To find out more, Isaac Kaplan-Woolner called the Wenatchee River Ranger

District.
    Resource Assistant Bob Stoehr said the total cost of the Upper Icicle Road

Project was $750 thousand. Some road maintenance work on the site may continue above the new construction site is

weather permits.
 