style="font-size: 14pt">Wednesday Morning—IKW

 
       Both of yesterday’s public meetings on the Leavenworth

Hatchery’s plans to build a new water system on the Icicle River were full of worried residents.

KOHO’s Isaac Kaplan-Woolner attended the evening session:

 
120209 hatchery

meeting—07:58

“Isaac

Kaplan-Woolner”

 
       Again, the Leavenworth Hatchery’s

water plan would essentially consist of an underground pump house, a low check dam across the canal, and a new dam

with a fish ladder across the Icicle River, just below the Sleeping Lady property. It would need NEPA approval by

the end of next September. For more on the hatchery plans, visit our website for a link.

"margin: 0in 0in 0pt"> 

When it comes to

multiple government agencies, hatchery salmon, and a pristine waterway with endangered wild fish, things can get

complicated in a hurry. The conference room at Leavenworth’s Enzian Inn was packed not once but twice on

Tuesday with concerned citizens. At stake are millions of one-time stimulus dollars for a desperately aging

Hatchery facility and/or the future of the icicle river watershed, depending on who you ask.

"margin: 0in 0in 0pt; text-indent: 0.5in">The Leavenworth National Fish Hatchery and the Bureau of

Reclamation presented a plan they say best meets their water needs, while best preserving the Icicle River.

Officials said the current seventy year old water pipeline is literally falling apart, and now the Hatchery has

access to $18 million in federal stimulus funds to fix their water intake system.

            The project would consist of

an underground pumping station, a low check wall dam at the top of the hatchery channel, and a replacement

“structure 2” dam with a new fish ladder across the river’s historic channel. The new intake

site is about .7 miles downstream of the current gravity fed water intake, and immediately downstream of the

Sleeping Lady resort.

            Federal Bureau of Reclamation Project

manager Ron Eggers facilitated much of Tuesday’s discussions. He said that while the dam and pump house

design plans are roughly 35% underway, there is still room for public input and discussion.

"margin: 0in 0in 0pt">            The plans must first

pass the muster of the National Environmental Policy (NEPA) process, which requires an environmental assessment,

or EA, which will be open to public comment. If the EA fails, it will trigger the more stringent Environmental

Impact Statement or EIS. But Eggers said that scenario could prove problematic:

 
            Dozens of residents asked questions and

posed challenges to the Hatchery’s proposed pump house and dam plans. Some asked Eggers if any of their

opinions would be taken into account:

 
            Still others challenged the

timing of the hatchery’s plans, claiming they were rushed to qualify for federal stimulus

dollars:

 
            Chelan County Commissioner Keith Goehner

said he felt the plan had been formed too much behind closed doors. He said that as a member of the Wenatchee

Watershed Planning Unit, he should have known about the hatcheries plans by now:

 
            The tone was intense throughout the two

hour-plus meeting, as people raised concerns about the existing irrigation ditch, the fate of wild fish under the

hatchery plan, why alternative plans were rejected, and why the current gravity fed system is not being

rehabilitated.

            Last to speak from the audience was

Leavenworth resident Pat Stroud, whose family built the original Icicle Irrigation system. Stroud said she remains

strongly supportive of a gravity fed pipeline similar to the one currently in use. But most importantly, she

supports the community gathering together to guide the future of the Hatchery:

 
            It seemed that many attendees left

Tuesday’s meetings with nagging questions or thoroughly entrenched in their opposition to the

Hatchery’s current water plans. Ron Eggers with the Bureau of Reclamation said the draft environmental

assessment of the pump house and dam plan should be out before Christmas, and that they will be seeking further

public comment.

 